LITTLE FALLS — What began as a routine maintenance operation Wednesday night has grown into a multi-day infrastructure emergency requiring specialized contractors, emergency valve installations, and around-the-clock crews working on sections of the city’s Main Street corridor.
The crisis began at approximately 11:00 p.m. Wednesday during scheduled hydrant flushing operations, when a significant leak developed on Main Street, believed to be associated with the hydrant lead serving Hydrant No. 59A. Water Department and DPW crews responded immediately and began working to isolate the break using existing distribution system valves.
Crews operated valves on John Street, Albany Street, Waverly Place, Main Street, Alexander Street, and Petrie Street in an attempt to contain the affected section of water main. The effort was complicated when multiple valves failed during operation, triggering several additional leaks and severely hampering the repair. Despite working through numerous valve locations across the area, crews were unable to achieve adequate isolation due to the deteriorated condition of the existing valve infrastructure.
As excavation work progressed, the volume of water entering the dig site could not be brought under control using the existing valve system — making a safe, effective repair of the primary leak impossible.
The City then began coordinating with contractor EJP and others to develop an emergency response plan, with insertion valves and other specialized measures identified as the path forward to isolate the affected distribution system sections.
With questions remaining about system isolation, officials grew concerned that water service to a nearby school could be disrupted. School representatives were notified and kept updated as conditions changed throughout the night. Benton Hall Academy does have water service.
Thursday, DPW crews worked alongside Horender Construction to excavate sites needed for EJP’s insertion valve work. One excavation was completed at the intersection of John Street and Main Street, where EJP successfully installed the first insertion valve.
As of midnight Thursday, EJP completed a second insertion valve at the intersection of Albany Street and Main Street. Field conditions at that location required modifications to the existing sewer system to accommodate the installation, adding complexity to the operation.
Simultaneously, DPW crews are excavating and preparing to repair the primary leak on Main Street. Assuming no unforeseen complications arise, that repair is expected to be completed Tuesday or Wednesday.
Looking ahead, the City also needs to replace valves serving the bus loop area in front of Benton Hall on Petrie Street. Horender Construction is scheduled to excavate for an additional insertion valve location on Monday at the intersection of Petrie and Ward Streets, with EJP returning Tuesday morning to install the new valve.
That work will require school coordination, as construction will impact the bus loop area. City officials will coordinate placement of temporary no-parking signs at the end of Petrie Street to accommodate the work.
At the intersection of Alexander Street and Burwell Street, crews plan to test the existing valve Tuesday morning. If that valve is found to be inoperable, an additional emergency excavation will be required.
Once EJP completes the insertion valve installation near Ward Street, they will shift to Alexander Street for another valve installation.