LITTLE FALLS – The news Little Falls residents have been dreading about the Connector Bridge finally has a number attached to it, and it’s a big one.

Ben Walsh, Director of the New York State Canal Corporation, brought a team to Little Falls on Wednesday afternoon for a follow-up on the project first outlined at a public meeting in April of 2023.

The update wasn’t the one people in the room were hoping for. Before the Canal Corporation can move forward with a bridge connecting Lock 17 to the Empire State Trail, Downtown and Canal Place, the agency says it has to sink $45 million into repairs at the lock itself – work that likely won’t even begin before 2028, and only then if nothing else slows it down.

Walsh didn’t dance around the disappointment. He opened by walking the room through some agency history – the Canal Corporation moved from the Thruway Authority to the New York Power Authority in 2017, a shift he said made sense given NYPA’s engineering and hydrology expertise, and its willingness to actually invest in the canal system.

That investment led to “Reimagine the Canals,” an initiative that looked hard at how the canal system is used today. It’s not commercial shipping driving traffic anymore – recreation is, and the Empire State Trail and Erie Canalway Trail alone bring in roughly four million users a year.

It was through that process, Walsh said, that the Connector Bridge concept at Lock 17 was born.

But the Reimagine initiative got paused, projects got re-evaluated, and priorities shifted. Rebecca, a member of Walsh’s team, offered the analogy that stuck with the room: working on a piece of infrastructure is a lot like working on an old building – this one included. You start pulling back layers expecting one thing, and you find more underneath.

That’s what happened at Lock 17. Once engineers started digging into the lock’s condition, they found the core infrastructure needed far more work than anticipated, and that work had to come first.

To be clear, officials say the bridge itself isn’t dead. It’s deferred, not abandoned. The broader project still includes streetscape improvements around Lock 17, work meant to make the lock area feel like more of a destination, along with tower and dam rehabilitation that will fold in a new, more accessible stairway so trail users can cross the dam on foot.

Still, the mood in the room ranged from disappointed to outright frustrated. People have been counting on the bridge as a safe way to get trail users off the Empire State Trail and into Downtown and Canal Place, and many said they doubted they’d live to see it finished.

One resident put it bluntly, telling the team they’d just wanted to hear that the promises made a decade ago were finally coming true.

Walsh acknowledged the skepticism head-on. He said, pretty pictures don’t mean much until a project actually gets delivered.

He was also straightforward about the sequencing. “The infrastructure has to take place before we can do anything else,” he told the group.

Mayor Deborah Kaufman moderated the discussion alongside members of the planning board, zoning board of appeals, and Common Council.

With the bridge on hold, the conversation shifted toward what the City and the Canal Corporation can do together in the meantime. Kaufman pointed to the work already done through the city’s Downtown Revitalization Initiative. She recalled residents once questioning why anyone would want to spend time near the water “where the factories used to be.”

These days, kayak rentals go for a few dollars an hour, fireworks nights draw kayakers onto the water, and the Sheriff’s Department and Fire Department turn out for the annual fishing tournament to keep an eye on the crowd.

Rotary Park has become a hub for river-adjacent programming, and Kaufman noted a visit from the historic replica ship Seneca Chief drew a crowd estimated at 2,000 people on its first stop, with a smaller but well-received educational return trip that brought roughly 150 to 200 students down to the water.

Canal Corporation staff also raised the Amsterdam pedestrian bridge as an example of what can happen when a project stays “shovel-ready.” That bridge, they noted, was partly funded through a congressional earmark, and staying prepared keeps Little Falls positioned if similar funding opportunities open up.

Before wrapping up, the team offered to help promote existing Little Falls events through the Canal Corporation’s own communications channels and pointed to a self-serve, wiki-style events calendar maintained by a sister canal organization that local groups can use to list their own programming.

No firm timeline exists yet for when Lock 17 repairs will begin beyond that 2028 target, and Canal Corporation officials made clear that date assumes no further delays – a caveat that, given the project’s history, wasn’t lost on anyone in the room.